Yes. A screw pile up to 1.5 m long can be screwed in by hand with a two-lever wrench, with no machinery and no crew. This is how Ø42, 60 and 76 mm piles go in under decks, gazebos, canopies and fences. A longer pile, 2–2.5 m, is turned by hand only when the soil allows it: in spring and autumn, when the ground is moist. Otherwise it is installed with machinery.
The larger the diameter and the length, the more effort it takes. 2–2.5 m piles are screwed in by hand only into moist soil, in spring and autumn. The limits are: in soft soils, up to Ø108 mm and 2.5 m; in medium soils, up to Ø89 mm and 2.5 m; in sand, up to Ø76 mm and 2.0 m. How many people you need depends on the soil. Otherwise a 2 m pile, such as SPGS F 60 × 3 × 2000 (650), is installed with machinery.
The wrench fits over the pile flange and is fixed with two M12 bolts. Two levers at least 2 m long go into the wrench, and the pile is turned by walking around it. A long lever gives more torque, so a short pipe will not do. We sell the wrench, and every pile order comes with marking-out and installation instructions. You will also need a spirit level.
If a pile suddenly stops or veers sharply to one side, it has usually hit a stone or construction debris. Do not force it: unscrew it, check the spot and move the point. We do not recommend screw piles on stony ground at all. A pile can be screwed in by hand in winter too, but it goes into frozen soil harder, so allow more time. More on this in our answer “Can screw piles be installed in winter?”.
If there are many piles or the soil is dense, doing it by hand is slow and hard work. The SP GS 1800 electric driver has 1800 W of power, up to 1800 N·m of torque and weighs 9.2 kg; it runs on 220 V mains. It installs Ø42, 60 and 76 mm piles up to 1.5 m long where machinery cannot get in: between buildings, on slopes, among plantings. It takes 2–3 people to work with the driver. We sell the driver; it is not available for hire.
We install 2 m piles and larger projects turnkey in Kyiv and the Kyiv region, using hydraulic rigs mounted on an AVANT loader and a MOROOKA tracked carrier. See Ground screw pile foundation installation for details. How deep a pile should go is covered in our answer “How deep should a screw pile be installed?”.
Send us the dimensions of the structure and the site address on +38 050 431-70-60 (Viber, Telegram, WhatsApp), and we will tell you which pile you can install yourself and which one needs machinery. All our standard pile models are in the Ground screw piles section.